Glendale seeks builder for $8M Arrowhead wastewater upgrades

Glendale opened an $8 million, five-year procurement for phased repairs and upgrades at the Arrowhead Ranch Water Reclamation Facility.

By Published

Glendale has opened a procurement for an estimated $8 million, five-year program of repairs and improvements at the Arrowhead Ranch Water Reclamation Facility in north Glendale.

The city’s request for qualifications was published Nov. 18 and seeks a construction manager at risk for the facility at 8180 W. Union Hills Drive. The selected firm would help during design and then handle construction under a series of guaranteed maximum price contracts as individual phases are defined.

The notice starts the contractor-selection process. It does not award an $8 million construction contract, establish a construction start or identify a completion date.

What the city is seeking

According to the city’s Nov. 18 procurement notice, reproduced in full by NoticeRegistry, the plant has operated for more than 40 years and last completed a major improvement project in 2021. That earlier work addressed treatment efficiency, odor control, filtration, electrical systems, instrumentation and plant controls.

Glendale completed an Integrated Water Master Plan in 2022 that recommended assessing the plant every five years. The new program is intended to identify repairs, rank the work and deliver improvements in phases rather than wait for another large catch-up rehabilitation.

The selected construction manager would initially advise the city and its design professional on planning, costs and construction issues. Before each construction phase, the city would negotiate a guaranteed maximum price. The notice says the approximately $8 million allocation covers design, construction and other associated costs over the next five years.

Glendale’s adopted fiscal 2026-27 budget lists Arrowhead Ranch Water Reclamation Facility upgrades among the city’s notable first-year capital projects. Water and sewer projects account for about $98 million, or 22%, of Glendale’s $441.2 million capital budget for the fiscal year.

Earlier plans identify likely systems

An earlier city capital plan described potential work on flow equalization, supervisory control and data acquisition equipment, aeration blowers, electrical systems and the effluent reuse distribution system. The same plan said the plant processes about 1.5 billion gallons of wastewater annually.

Those items provide project history, but they should not be treated as the final construction package. The new procurement says assessments will identify and prioritize repairs, and each phase will require its own scope and guaranteed maximum price.

Next milestones

Glendale scheduled a virtual pre-submittal conference for Dec. 9 at 2:30 p.m. Qualifications are due Dec. 17 by 2 p.m. under Project No. 232415 and Bid No. 42700027.

After proposals are reviewed, the city would need to select a construction manager and complete contracting before design assistance and phased construction can proceed. The notice does not identify customer service interruptions, a utility-rate change or a firm schedule for physical work.

Featured image: Representative editorial illustration of municipal water-reclamation infrastructure. It does not depict the Arrowhead Ranch facility.

More from West Valley Post

Discussion

Comments

Join the conversation. Keep comments relevant, civil and focused on the story.

Leave a comment

Your email address will not be published. Required fields are marked *.