Sun City’s Mountain View Recreation Center is scheduled to close Sunday, Nov. 29, for a $30.1 million reconstruction project that Recreation Centers of Sun City expects to continue into 2028.
The closure applies to the site at 9749 N. 107th Ave. RCSC’s final design presentation, dated Nov. 17, says the property will close for pre-construction and construction activities. The schedule calls for construction to begin in December and last about 22 months, with completion targeted for mid-to-late 2028. RCSC cautions that the dates could change.
The long closure will remove one of Sun City’s recreation campuses from use while RCSC replaces or rebuilds major facilities. The center serves the unincorporated Sun City community, so the project is being managed by RCSC rather than a municipal parks department.
A new recreation campus
The final design combines a performance venue, fitness facilities, aquatics, court sports and outdoor gathering areas on the Mountain View property.
Plans show a performance building with a stage, curved audience seating, lobby, ticket booth, concessions, dressing rooms, technical rooms and backstage work and storage areas. The adjacent fitness building is divided into cardio, strength, functional training, stretching and recovery areas, plus a multipurpose room and locker rooms.
The aquatics plan retains the existing resort pool and adds a pool house with locker rooms, storage and deck shade. Other planned elements include a new clubhouse, six pickleball courts, a shared barbecue area, tennis and pickleball storage, a mini-golf building with shaded seating, connected walking paths and landscaped gathering spaces.
RCSC’s board selected an amended “Option 3B plus” plan on Jan. 29. A March RCSC project update said the decision added a new clubhouse and a new mini-golf building and raised the project’s “all-in” budget to $30.1 million. That figure is the board-approved project budget described by RCSC, not a newly announced construction contract award.
Work begins while documents and permits advance
The project remains in a transition from design into construction. RCSC’s schedule places construction-document work between September 2026 and January 2027. Bidding and permitting are scheduled from December 2026 through April 2027, overlapping with the planned December construction start.
That sequence means the Nov. 29 closure and early construction activity do not establish that every permit, bid package or construction contract for the full project is complete. RCSC’s presentation does not identify a final construction contract amount or provide a detailed opening date beyond the mid-to-late 2028 target.
The RCSC Mountain View project page collects the organization’s presentations and project updates. The next measurable milestones are the December groundbreaking and start of construction, followed by completion of construction documents in January and the bidding and permitting phase now scheduled through April.