Avondale opened bids for a $4.5 million rehabilitation of the 10th Street Lift Station, which serves northwest portions of the city.

By Published

Avondale has opened contractor bidding for a $4.5 million rehabilitation of its 10th Street wastewater lift station, advancing a funded utility project that will replace major pumping, piping, electrical and odor-control systems.

The city released solicitation PW 27-019 on Nov. 19. Bids are due Jan. 7, 2027, at 5 p.m. Arizona time.

The procurement is a construction milestone, but work has not started. Avondale has not selected a contractor, established a final contract price or published a construction start and completion schedule.

A new station within the existing site

The bid documents call for construction, startup and commissioning of a new lift station within the footprint of the existing 10th Street facility. Selected parts of the current station would be demolished.

Major work includes a new wet well, submersible pumps and motors, mechanical piping, a buried high-density polyethylene force main and a connection to the existing force main. A lift station collects wastewater at a low point and pumps it into a pressurized pipe when gravity alone cannot move it toward the treatment system.

The contractor also would provide temporary bypass pumping so the sewer system can remain in service while the station is rebuilt. Other listed work includes replacement electrical equipment and site lighting, an odor-control unit, a lifting crane, a new entrance gate and masonry wall, an emergency eyewash station, concrete work and a new site driveway.

The scope is broader than an electrical-only replacement. Avondale’s current capital plan labels project U0369 as the 10th Street Lift Station Rehabilitation and assigns it a total project budget of $4.5 million. The city’s fiscal 2027 budget materials list $4.158 million in planned fiscal 2027 spending and $58,000 in carryover for the project.

Those figures describe the city’s budget, not an awarded construction contract. The bid results will determine the proposed contract amount before the city can move toward an award.

Station serves northwest Avondale

An earlier city capital-improvement report said the 10th Street Lift Station conveys more than 1 million gallons of wastewater per day from northwest Avondale.

That report described the station’s associated force main as extending about 4,700 feet south along Eliseo C. Felix Jr. Way to Van Buren Street, then east across the Agua Fria River to Fairway Drive. At the time, the city was evaluating the line because restricted access prevented staff from inspecting it for deficiencies.

The new solicitation specifies a buried force-main segment and connection at the station. It does not state that the entire 4,700-foot alignment will be replaced, so the current work should not be read as a full replacement of the older line unless Avondale establishes that in later records.

Lift stations operate in a corrosive environment, where pumps, motors, piping and controls require periodic replacement. Avondale’s prior budget documents also identified aging equipment and odor generation as recurring maintenance concerns across the city’s lift-station network.

What happens next

Avondale scheduled a nonmandatory online pre-bid meeting for Dec. 8 at 2 p.m. Contractors may submit questions through Dec. 23, and bids close Jan. 7.

After the deadline, the city will evaluate the submissions and decide whether to recommend an award. The records available Friday do not identify a target council date for that decision.

The next useful milestones are the bid tabulation, contractor selection, final contract amount and construction schedule. Residents also should watch for any notice describing temporary access, odor or service impacts during bypass pumping. The city’s solicitation does not announce a customer service interruption.

The project is part of a broader cycle of West Valley utility reinvestment. Glendale recently opened an $8 million procurement for phased work at the Arrowhead Ranch Water Reclamation Facility, another example of cities upgrading existing wastewater infrastructure as the region grows.

Featured image: AI-generated editorial illustration representing a municipal wastewater lift station. It does not depict Avondale’s actual 10th Street site, an approved design or an engineering plan.

More from West Valley Post

Discussion

Comments

Join the conversation. Keep comments relevant, civil and focused on the story.

Leave a comment

Your email address will not be published. Required fields are marked *.