Skip to content
Surprise ICE facility water demand triples earlier estimate
Local News

Surprise ICE facility water demand triples earlier estimate

A Surprise utility analysis estimates the proposed ICE facility would use 190,000 gallons daily and face nearly $9 million in utility obligations.

By Published Updated

A City of Surprise utility analysis says the proposed immigration detention facility on Sweetwater Avenue would use about 190,000 gallons of water on an average day, roughly three times the demand anticipated when the warehouse was built.

The September 22 letter from Surprise Water Resource Management also assigns the proposed facility nearly $8.94 million in specified water, wastewater and water-resource obligations before development impact fees and future cost adjustments. The building remains on hold for detention conversion while a federal environmental review proceeds.

ABC15 reported on the updated figures Thursday night. The underlying six-page city letter was sent to GardaWorld Federal, the contractor tied to the project, and evaluates projections the company provided to Surprise on August 10.

Water demand is three times the warehouse estimate

The April 2023 water report prepared for the existing industrial building estimated average demand of 63,000 gallons per day and maximum-day demand of 126,000 gallons.

The new facility projection identifies 190,000 gallons per day of anticipated water demand and 215,000 gallons of peak usage. For infrastructure planning, city staff treated 190,000 gallons as the average-day demand and applied the two-times maximum-day factor in Surprise’s water plan. That produces a maximum-day planning demand of 380,000 gallons, 254,000 gallons above the earlier warehouse estimate.

The city says the additional demand would require a new groundwater well in the Rancho Gabriela pressure zone about five years earlier than planned. The well would need to provide approximately 176 gallons per minute. The facility’s proposed 800,000-gallon onsite reservoir would also need to be filled under city-approved rates and operating conditions while the municipal system continues meeting other demand.

Specified obligations total nearly $8.94 million

The city letter lists four major obligations for the facility:

  • $6,117,620 for a new groundwater well and associated improvements.
  • $921,008 for design changes and additional arsenic-treatment capacity at the Rancho Gabriela Water Supply Facility.
  • $839,600 as a proportionate contribution toward wastewater-treatment capacity.
  • Either 1,512 acre-feet of qualifying water resources covering 15 years or a city-approved payment currently calculated at $1,058,400 for long-term storage credits.

If the facility uses the cash option for the water-resource obligation, those four amounts total $8,936,628. That calculation does not include applicable development impact fees, onsite pretreatment equipment, a water meter and backflow assembly, or cost escalation before payment.

The existing eight-inch sewer line may have enough capacity for the proposed flow, according to the analysis, but that must still be confirmed. The facility would also have to comply with city and federal wastewater pretreatment requirements.

Legal hold and capacity questions remain

U.S. Immigration and Customs Enforcement owns the 418,000-square-foot warehouse at 13290 W. Sweetwater Ave., near Dysart Road. A Government Accountability Office report released September 24 says ICE obligated $313 million for renovation and still intends to use the Surprise property, even after moving to sell seven of 11 warehouses purchased for a national detention expansion.

The $313 million renovation obligation is separate from the roughly $70 million property purchase reported from Maricopa County records by Arizona’s Family.

Arizona Attorney General Kris Mayes sued the Department of Homeland Security and ICE in April, alleging the agencies moved toward conversion without completing the environmental review required by federal law. Under a stipulated agreement announced July 1, federal officials may not detain anyone at the property or begin detention-related construction, demolition or retrofitting until they complete an environmental assessment and issue a final decision document.

The new utility analysis does not lift that hold, approve construction or establish an opening date. It identifies what Surprise would require if the project advances and seeks city water and wastewater service.

Final operating capacity also remains unsettled. Early federal documents described space for as many as 1,500 people, while Surprise Mayor Kevin Sartor said in March that DHS had reduced the plan to a maximum of 542 occupied beds. Neither the GAO report nor the state’s court agreement establishes a final capacity.

The next measurable steps include completion of the federal environmental review, resolution of the project’s capacity and design, confirmation of sewer capacity, and any sustainable water-service agreement covering the required water resources and infrastructure payments.

Updated October 2, 2026, to add the City of Surprise water and wastewater analysis, projected demand and utility obligations.

More from West Valley Post

Discussion

Comments

Join the conversation. Keep comments relevant, civil and focused on the story.

Leave a comment

Your email address will not be published. Required fields are marked *.