Maricopa County approved a 5,381-acre zoning expansion for a planned solar generation and battery storage complex in the Harquahala Valley, about 20 miles west of Buckeye.
The Board of Supervisors approved the paired land-use cases on Nov. 18. Case CPA260006 changes the comprehensive-plan designation on an 80-acre parcel from Rural Development Area to Utilities. Case Z260016 rezones approximately 5,381 acres from rural zoning to an industrial district with an overlay that limits the property to solar generation, battery storage and related uses.
The county’s formal meeting record marks the rezoning approved. The county staff report and project narrative establish the acreage, location, prior approvals and conditions.
The decision is a land-use approval. It is not a construction start, building permit or confirmation that the entire project will be developed at once.
How the project reached roughly 14,429 acres
The original Harquahala Sun III-V project covered approximately 9,047.58 acres. County records say the Board approved its major comprehensive-plan amendment in December 2022 and its industrial zoning and development plan in July 2024.
A second land-use expansion covering about 5,461 acres received comprehensive-plan approval in December 2025. The Nov. 18 action completes the zoning process for roughly 5,381 acres of that expansion and brings the remaining 80-acre parcel into the Utilities land-use category. Applicant materials calculate the combined planned project area at approximately 14,428.93 acres.
The documents use two similar names. The Board agenda calls the cases the “Harquahala Sun III-IV Expansion,” while the zoning narrative and exhibits call the site “Harquahala Sun III-V Additional Land.” Both refer to cases CPA260006 and Z260016.
The project area is generally west of Harquahala Valley Road near Baseline Road, southwest of Saddle Mountain and north and east of the Eagle Tail Mountains. It spans state and private land in unincorporated western Maricopa County.
What the approval allows
The approved IND-2 IUPD zoning restricts the site to a solar electric generation and battery storage facility, including ancillary offices and supporting infrastructure. A different industrial use would require another major zoning amendment.
The conditions require project equipment and infrastructure to remain at least 200 feet from Centennial Wash. The wash must remain open and fenced off from project areas. Wildlife provisions include elevated fence segments at intervals and construction practices intended to reduce invasive plants and protect animals from open trenches.
Road and access details remain preliminary. County staff says access from Interstate 10 would use Harquahala Valley Road. Future development plans must include traffic analysis, and the county can require additional right of way or off-site road improvements after reviewing that work.
The current case materials do not identify a final generating capacity, battery capacity, investment amount or construction schedule for the expanded site. Those omissions are important because the acreage approval defines where the project may be developed but does not establish how much equipment will be installed or when it will operate.
What must happen before construction
The developer must submit one or more plans of development for administrative county approval. Those filings will need engineered grading and drainage plans, traffic studies and more detailed site layouts. Building permits, floodplain permits where applicable, dust-control requirements and other construction approvals would follow.
The conditions also require confirmation that the facility meets the requirements of the responsible fire-protection jurisdiction before building permits are issued. The project must receive fire review before occupancy, complete an informal review through the U.S. Department of Defense Siting Clearinghouse and comply with wildlife studies or mitigation requested by the Arizona Game and Fish Department.
The next records to watch are the administrative development plans, final capacity figures, traffic study, utility interconnection information and construction permits. Until those appear, the project should be described as approved for solar and battery use, not under construction.
The approval adds another large energy proposal to the western edge of the region. In September, West Valley Post reported on Goodyear’s approval of the 5,050-acre Desert Rainbow solar and storage project, which remains in development.
Featured image: AI-generated editorial illustration representing utility-scale solar and battery storage in the Sonoran Desert. It does not depict the Harquahala project site, an official rendering or an approved site plan.