APS 1,280-MW Desert Sun gas plant heads to Dec. 9 vote

Maricopa County will consider zoning for APS’s proposed 1,280-megawatt Desert Sun natural-gas plant west of Gila Bend on Dec. 9.

By Published

GILA BEND, Ariz. | Nov. 21, 2026. A proposed 1,280-megawatt Arizona Public Service natural-gas power plant west of Gila Bend is scheduled for a Maricopa County Board of Supervisors zoning hearing on Dec. 9.

The hearing is the next land-use decision for the Desert Sun Power Plant, not final authorization to begin construction. APS still needs air-quality, transmission, site-development and construction approvals before the plant could operate.

The county hearing packet posted Nov. 20 covers comprehensive-plan case CPA260009 and rezoning case Z260022. The Planning and Zoning Commission recommended both requests 7-0 on Nov. 5.

APS is seeking to change the land-use designation from Rural Development Area to Utilities and rezone the property from Rural-190 to an industrial planned-development district restricted to a natural-gas energy facility.

What APS is proposing

The site covers approximately 1,270 acres at the northeast corner of Powerline and Painted Rock Dam roads, about 13 miles west of Gila Bend. County records describe four privately owned parcels now used as agricultural fields.

APS proposes two combined-cycle generating units, each rated at about 640 megawatts. Each unit would pair a GE Vernova 7HA.02 combustion turbine with a steam turbine, producing electricity from both natural-gas combustion and recovered exhaust heat.

According to APS’s current project page, construction could begin in 2028 if required approvals are obtained, with completion estimated in 2031. The zoning record says the plant is expected to support 45 permanent jobs.

The current proposal is smaller than the project APS announced in October 2025. That announcement described a site capable of producing up to 2,000 megawatts. APS now says it moved what had been Desert Sun’s first phase to the existing Saguaro Power Plant site in Pinal County. The remaining Gila Bend proposal is the 1,280-megawatt facility now before the county.

Growth and data-center demand

County planning documents say the plant is intended to serve large new electrical loads, including data centers and other energy-intensive customers. APS has separately described a “growth pays for growth” strategy under which large customers would cover costs tied to serving their demand.

The documents do not identify a specific data-center customer for Desert Sun. The link to data-center growth is significant because APS is also involved in transmission and generation planning around other large West Valley computing campuses, including the Project Eagle and Baccara campus approved in Glendale.

Desert Sun would also require new high-voltage infrastructure. APS’s transmission project description calls for two new lines running approximately 20 miles east to a new substation. Each line would carry 500-kilovolt circuits and have capability for 230-kilovolt circuits. APS expects the transmission work to be completed in 2030, subject to a separate siting process.

Air permit and other reviews remain

APS submitted an air-quality permit application in May 2026. The application classifies Desert Sun as a major stationary source under federal Prevention of Significant Deterioration rules for several pollutants and greenhouse gases.

The application calculates annual potential emissions of 329.7 tons of carbon monoxide, 326.6 tons of nitrogen oxides, about 160 tons each of particulate matter categories, 106 tons of volatile organic compounds and approximately 4.1 million tons of carbon-dioxide equivalent.

Those figures are the applicant’s potential-to-emit calculations under specified operating assumptions. They are not measured emissions from an operating plant or final permit limits. APS’s modeling concludes the proposed controls would meet applicable air-quality standards; the permitting process will determine enforceable limits, monitoring and operating requirements.

County staff also flagged the site’s proximity to Interstate 8 and Gila Bend Auxiliary Airfield, which is about 10 miles east and records more than 30,000 annual aircraft operations. Recommended zoning conditions require Arizona Department of Transportation review and limit electrical and transmission structures to 200 feet. A detailed plan of development and traffic study would still be required.

What happens next

The Board of Supervisors can approve, deny or continue the two land-use cases on Dec. 9. An approval would establish the planning and zoning framework, but it would not confirm a construction start.

Major remaining milestones include a county plan of development, the air permit, transmission-line siting, utility and infrastructure approvals, and construction permits. APS’s 2028 start and 2031 completion dates remain planning estimates until those steps are completed.

Featured image: Representative photograph of APS’s Ocotillo natural-gas power plant in Tempe, not the Desert Sun site. Photo by Alan Stark, CC BY-SA 2.0, via Wikimedia Commons.

More from West Valley Post

Discussion

Comments

Join the conversation. Keep comments relevant, civil and focused on the story.

Leave a comment

Your email address will not be published. Required fields are marked *.